In the matter of Ramesh Kumar Mishra V/s Bhopal Development Corporation (M-BPL-18-0118) Order dated: 17th April 2018 Madhya Pradesh RERA disallowed the promoter for asking last payment because of amenities yet to be provided. .
The Complainant had been allotted a plot in Aerocity Phase I by the Respondent on 1st May 2015. The Complainant was to pay the consideration in four instalments to the Respondent according to the offer. Complainant maintained that since the roads and other facilities are not complete he refused to take the possession of the plot and not paid last instalment due to the Respondent. He also maintain that after he execute the transaction, the maintenance charges will be started by the Respondent. The Respondent accepted that the development work is not complete in the scheme.
MP RERA Ordered: Respondent is eligible to ask the last instalment only when the development work is over in all aspect and till than no interest can be charged from the Complainant.